Tuesday we spent most of the day at the new source (near the existing spring box/source). Amed and a large crew were in place and working by the time we arrived. There were approx 30 people digging and moving dirt and another 15-20 carrying rocks and sand on their heads to the site.
Great progress and we will return on Thursday to check progress, however all work will likely take 8-10 days to complete.
We hiked back to Muhuroro, arriving at dusk. We met Amed for a drink (Coke) at a local bar. We then walked to the orphanage by Pat's headlamp and the light of my gps - not recommended!